The floor is rather special, not just concrete, it has a compound blended into the surface when it is still setting, this gives it an harder than usual surface, very important over here, when in the winter time we are driving with studded tyres, they can easily destroy the surface of the floor if it is just painted, even bare concrete cannot withstand the rigours placed upon it with studded tyres.
PUTTING THE CONCRETE DOWN. All in all it took 6.2 cubic meters of concrete for the floor, depth of concrete is 10cm.
LEVELLING IT OUT. A job for a specialist, certainly not for me, it is the kind of work that requires years of practice, best to hire the right people for the job, these guys are really good, We have used them on all our previous projects and I've recommended them to countless others.